A414 Edinburgh Way, Harlow: Concrete Road Reinstatements
Essex County Council's A414 Edinburgh Way widening scheme needed new services run beneath a live trunk road without shutting down the industrial estate it serves. Morgan Sindall had already cut in the services and backfilled with temporary asphalt; TAG's job was to reinstate the concrete carriageway behind them, permanently and to a standard that would take the road's full weight of daily HGV traffic.
TAG supplied and managed every resource needed to get the job done, bar the road closure itself: labour, plant, specialist sub-contractors, saw cutting, sweepers, waste disposal, welfare facilities and rapid-setting concrete, all mobilised for restricted night closures running Monday to Friday, 20:00 to 06:00.
The challenge was the clock. Each bay had to be saw cut, broken out, excavated, dowelled and poured with a new CSA concrete before the 06:00 handback, with no room for overrun on a road that would be carrying heavy industrial traffic within the hour. TAG's calcium sulphate aluminate mix cured to 25-30N/mm² in as little as two and a half hours even in low temperatures, and its consistency let the team pour to the road's camber without slumping.
TAG arrived, worked and demobilised each shift without needing a compound or site set-up, and the road reopened to Edinburgh Way's heavy goods traffic on schedule every morning of the programme.
Key Facts
Client
Morgan Sindall Infrastructure
Location
A414 Edinburgh Way, Harlow, Essex
Closure window
20:00–06:00, Mon–Fri
Concrete cure time
25–30N/mm² in 2hrs 30